ENV-9
Approve Resource Agency Public Notice

Description: This key decision is required to satisfy the regulatory requirement for Section 404 permitting that the public receive notice of a permit application. There is no integration with other phases of transportation decision making or other decision making processes.

Note that changes to the project could occur as part of design that would require a modified Section 404 (or other) permit application and the approval of a new resource agency public notice.



  • Basics
  • Integration
  • Decision Making Questions
  • Case Study Examples
  • Technical Support
  • Special Topics

Purpose

To inform the public that a Section 404 application has been received, describe planned activities and enlist public comment with regard to the project.

Outcome

Public comments, necessary to evaluate the probable impact of the project on the public's interest, are received.


Partner Roles

FHWA

No Role

Action required only by federal permitting agency(s)

MPO

No Role

No action required for permitting Public Notice

Resource Agency

Decision Maker

USACE is a decision maker, approving a public notice that is consistent with 33 CFR Part 325.3

State DOT

Observer

Observes the public notice required for permitting


Process

Integration Type

Integration Description

Land Use and Smart GrowthNone.None.
Air Quality ConformityNone.None.
Natural Environment and the IEFNone.None.
Capital ImprovementNone.None.
Safety and SecurityNone.None.
Human EnvironmentNone.None.
Economic DevelopmentNone.None.
Greenhouse GasNone.None.

Linkages to other Phases of Transportation Decision Making

None.


Policy Questions

Questions about purpose and roles

No specific questions.

Questions about stakeholders

No specific questions.

Questions about the transportation process supporting the decision

Does the public notice meet federal requirements?

Questions about other phases

No specific questions.

Questions about non-transportation sectors/processes

No specific questions.

Questions to Gather Stakeholder Interests

None.

Questions to Incorporate Stakeholder Interests

None.


Case Study Example(s):

None.

Supporting Data for the Key Decision

InfoThe following is a list of data needed to support the key decision. Practitioners collect this information for decision makers to consider. You may add to this list using the comment box at the bottom of the page.

From other phases of transportation decision making

Long Range Planning

No Specific Data

Programming

No Specific Data

Corridor Planning

No Specific Data

Environmental Review

No Specific Data

From other sectors and processes

Land Use and Smart Growth

No Specific Data

Air Quality Conformity

No Specific Data

Natural Environment and the IEF

No Specific Data

Capital Improvement

No Specific Data

Safety and Security

No Specific Data

Human Environment

No Specific Data

Economic Development

No Specific Data

Greenhouse Gas

No Specific Data

From the transportation technical process supporting this key decision

Section 404 permit application

From stakeholder collaboration

No Specific Data

From public private partnership

No Specific Data

Supporting Tools and Technology

None.




Key Decision Relationship to Other Topics

Topic Description
Streamlining a Bottleneck Project
Approve Public Notice
Data Transfer - None


We invite your comments/concerns about this website and its contents. Please send us an email at transportationforcommunities@gmail.com.